Notice
Stage 5: Follow up notice
Step
5.1
For: Inspector
Is a follow up visit required?
A follow up visit is required to check compliance with the notice,
unless the circumstances described in step 5.2 apply
when a follow up visit is to be made:
Wherever practical, the follow up visit should be paid by the inspector
who served the notice but if there are grounds to suspect that it will
not have been complied with, the follow up visit should, where necessary,
be paid with a colleague to provide evidence in any subsequent legal proceedings.
If an improvement notice or a deferred prohibition notice has
been served:
- consider the need to contact the dutyholder beforehand and remind them to take the required
action by the due date.
Performance standards
If an immediate prohibition notice was served and the dutyholder stopped
the work activity but remedial control measures had not been implemented
before the inspector left the site, a follow up visit should be paid:
- if the dutyholder is likely to resume the activity
- after a period determined by knowledge of the dutyholder and the
original circumstances
For an improvement notice, a follow up visit should
be paid:
- as soon after the expiry date as possible
- always within 10 working days of this date
For a deferred prohibition notice, a follow up visit should be
paid:
- as soon after the expiry date as possible
- always within 10 working days of this date
Back to top
Step
5.2
For: Inspector/line manager
Is follow up without a visit appropriate?
A follow up visit to check compliance with an improvement notice may
not be required where:
- the notice relates to a statutory provision for documentation to
be held or provided, and
- verification may be achieved equally effectively by reviewing the
documentation in the inspector's office
Note: the date of receipt of the relevant
documentation should be recorded
Where it is not practicable to make a follow-up visit to check
compliance with an immediate prohibition notice, alternative types of
follow-up action may be appropriate in these circumstances:
- the risk of serious personal injury had been controlled by the dutyholder suspending
the activity and the inspector was able to confirm that remedial
measures had been taken before they left the site
or
- the risk of serious personal injury had been controlled by the dutyholder suspending
the activity but remedial measures had not been implemented before the inspector
left the site, and
- the inspector is confident the dutyholder will take the necessary
measures before resuming activities, and
- sufficient correspondence/documents have been sent by the dutyholder
by an agreed date which confirm action taken that will adequately
control the risk, and
- final closure is agreed by the line manager
In all cases:
- record the reasons for not conducting a follow up
visit, including the line manager's agreement, where
appropriate
Back to top
Step
5.3
For: Inspector
Has the notice been complied with?
Where the notice has been complied with:
- confirm this outcome with the dutyholder
- inform any employee representatives
- record the findings of the check visit
- where required, retain an appropriate hard-copy report
In ND:
- all notices should be reviewed by the Inspection Coordination Group
(ICG) within 12 months of closure for effectiveness against HSC's
Enforcement Policy Statement and the outcome recorded on the standard form
provided
- any lessons learned should be promulgated throughout ND and be
forwarded to the Business Systems Manager to facilitate the
improvement of procedures and guidance
In all cases where the notice has not been complied with:
- sufficient evidence should be collected to prove the related breach on the day of the visit and/or non-compliance with
the notice, with a view to recommending prosecution
- record findings of follow up visit
For guidance on this, please see:
go to: Step 1.1 prosecution
procedure
Back to top
Step
5.4
For: Inspector/line manager
Has an extension been requested?
A dutyholder may request an extension of the notice period but
must do so:
- during the period of compliance with an improvement notice; or
- before the period of compliance with a deferred prohibition notice
If the request falls outside this period:
Where the dutyholder requests
an extension within the appropriate period:
- discuss with them their reasons for the request
- decide whether the need for an extension is genuine and justified
If minded to grant an extension:
- decide whether written confirmation of the request is required, or
- a properly minuted account of a verbal request is sufficient, and
- where necessary, discuss the request with the line manager, e.g. where
the dutyholder has engaged a contractor to carry out the work but not
promptly after the notice was served
If an extension is granted:
- send form LP4 by recorded delivery to the dutyholder within 5 working
days of the request and in any case before expiry of the compliance
or notice period, unless
- the expiry date is imminent, then inform the dutyholder promptly of
the decision and confirm a positive decision on form LP4 within 5 days
of receipt of the request
- send copies of form LP4 to all the recipients of the original notice
- record the date the request was received, the action taken and reasons for the decision
If an extension is not granted:
- inform the dutyholder as soon as possible and in any case before
the expiry of compliance or notice period
- record the date the request was received, the action taken and reasons for the decision
Back to top
Step
5.5
For: Inspector and line manager
Should withdrawing the notice be considered?
Where a request to withdraw the
notice before the compliance date is made by the dutyholder:
- assess the request in consultation with line manager
- only withdraw the notice where there is a genuine and justifiable
need, including that it contains a significant error
If the notice is not to be withdrawn:
- inform the dutyholder of the decision within 5 working days of the
request and in any case before the expiry of the compliance or notice
period
- record date of request and reasons for action taken
If the notice is to be withdrawn:
- complete form LP5 and send it to the dutyholder within 5 working
days of the circumstances coming to the inspector’s attention and
in any case before the expiry of the compliance or notice period, unless
- the expiry period is imminent, then inform the dutyholder promptly
of the decision and confirm the withdrawal in writing within 5 working
days
- copy the LP5 to all the recipients of the original notice; a covering
letter of explanation may be required
- record date of request and reasons for action taken
Following withdrawal:
- consider the need to issue a new notice
Next: Stage 6: Respond to an appeal