HSE banner

Chapelcross Power Station

Site Stakeholder Group

Quarterly report for 1 October to 31 December 2006

Contents


Foreword

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Chapelcross Site Stakeholder Group (SSG) and covers activities associated with the regulation of safety at Chapelcross Power Station. These reports are distributed quarterly and are available also from the Internet at http://www.hse.gov.uk/nuclear/index.htm. Site Inspectors of HM Nuclear Installations Inspectorate (part of the Health and Safety Executive’s Nuclear Directorate) attend SSG meetings and will be happy to respond to any questions raised there or subsequently by members of the SSG. Any other person wishing to inquire about matters covered by this report should contact the HSE’s, Nuclear Directorate on 0151-951-3484/3290.

Nuclear Directorate
Health and Safety Executive
Redgrave Court
Merton Road
Bootle
Merseyside
L20 7HS

[back to top]


Inspections

The HMNII Site Inspector made the following planned visits during the period:

  • 9-13 October,
  • 24-25 October,
  • 1-2 November,
  • 6-10 November,
  • 21 November,
  • 28 November - 1 December,
  • 19-21 December

A team of HMNII inspectors undertook an inspection on management of organisational change as one of a series of themed inspections across defuelling and operational MEL licensed sites.

The NII site inspector undertook a joint inspection with the SEPA site inspector on liquid effluent.

[back to top]


Routine matters

Compliance with Site Licence Conditions

Routine inspections continued throughout the period to check compliance with the conditions attached to the Nuclear Site Licence.

Progress continued to be made on removing radioactive waste that has accumulated on the site, and on the provision of a radioactive waste processing facility.

Incidents on Site

The management and recording of events that occurred on the station during the period were inspected. Most of the events were relatively minor, although one is highlighted below.

A significant fall of asbestos from one of the heat exchangers occurred on 4 December 2006. Nuclear safety was maintained at all times during and after the incident. An inspection has been arranged with HSE’s asbestos specialists to determine how Chapelcross plans to deal with asbestos on the site.

Meetings attended

The following routine meetings were attended:

Chapelcross Site Stakeholder Group – 1 December

[back to top]


Non-routine matters

Fuel Route Improvement/Defuelling Project

Modification work continued on the upgrading of the fuel route discharge machines and associated plant, and our assessment work on related matters continued. Testing of systems continued and commissioning to integrate the systems started, along with training of staff. As a result of the increased activity, the number of inspections increased during the period and HMNII undertook inspections at Chapelcross on training, commissioning, mechanical engineering, electrical engineering, radiation protection and quality assurance.

[back to top]


Regulatory activity

Site Licence:

The Inspectorate has powers under the Nuclear Site Licence to issue regulatory documents collectively termed Licence Instruments. These Licence Instruments are issued under the licence conditions and arrangements and include Consents, Approvals, Directions, Specifications, Notifications and Agreements. The following licence instrument was issued during the quarter:

Under Health and Safety Legislation the Site Inspector, or other HSE Inspectors, may issue formal notices to secure improvements to safety. No such notices were issued during the quarter.

[back to top]